Governor Babajide Sanwo-Olu has reiterated his administration’s commitment to deliver the 27-kilometers Lagos Blue Line Rail Mass Transit by December.

Governor Sanwo-Olu made the promise during the launch of the last track beam of the rail track on Wednesday.

Speaking at the launch, Sanwo-Olu said the achievement signposted his administration’s commitment to bringing succour to Lagosians and give them choices in mass transportation.

The Governor maintained that the rail projects represented the audacity of his administration’s vision to deliver a robust integrated transit system as encapsulated in the Traffic Management and Transportation pillar of his Government’s development agenda.

With the laying of the final T-Beam, all difficult civil works standing in the way of the Lagos Blue Rail Line, which started in 2012, have been overcome. The contractor will now go ahead to set the rail tracks along the alignment and move the project to completion.

The Governor said the rail projects represented the audacity of his administration’s vision to deliver a robust integrated transit system as encapsulated in the Traffic Management and Transportation pillar of his Government’s T.H.E.M.E.S. development agenda.

He said: “Today’s final T-beam launch indicates that we are gradually inching to the completion of the civil infrastructure for the first phase of the Blue Line traversing from Mile 2 to Marina. The engineering work today completes a total of 1,967 piles foundation, while we have also completed three 306 platforms, 310 piers, 267 cover beams and erection of 984 T-beams.

“We are not just making promises; people are beginning to see for themselves that all the milestones and the difficult tasks we are meant to achieve to ensure operation of the Blue Line are being achieved. The Marina Station, which is the iconic terminal for the Blue Line, will be completed within two-and-half months. I am restating here that we will formally complete this Blue Line before December 31, 2022.”

The Governor said the two sets of EMU coaches already procured for the Blue Line operations would arrive in Lagos from China before the end of October. He said the rail line would be test run immediately after completion, while passenger movement would start within the first quarter of 2023.

Sanwo-Olu said the construction of the second phase of the Blue Line project would commence after the start of operation, which would extend the rail project from Mile 2 to Okokomaiko.

He said Blue Line stations would be built at Festac, Alakija, Trade Fair, Volkswagen, LASU and Okokomaiko. The Governor disclosed that talks were being held with the Ogun State Government for possible extension of the rail line to Agbara.

He said: “The second phase of the Blue Line project will be an easy infrastructure to develop because the marked alignment for stations and tracks are largely at grid level. While we are at this, the Red Line is also on the way. This is a start-and-end project for our administration, with about seven stations concurrently being built. This will redefine mass transportation in Lagos.

“To our citizens, I say the Blue Line is for real and you will ride on it in no distant future. For the Doubting Thomases and people that do not like our face, their eyes cannot disbelieve in the infrastructure we are bequeathing to the citizens of our State. They cannot disbelieve in our bold effort and commitment to improve mobility and deliver transport infrastructure that brings ease to our people.”

On his part, LAMATA Managing Director,  Abimbola Akinajo, said the first 13-kilometre stretch of the Blue Line construction was divided into four phases to enable the government fund the project from its internally generated revenue.

To get to the current status, she said the construction work experienced disturbances and delays in the relocation of submarine cables, submarine natural gas pipelines, and removal of underground shipwrecks.

 

 